Construction Updates

Rendering of Fierke addition.

Project Details

Fierke is creating additional space to accommodate the full-day kindergarten program. 

Additions include:

  • Three kindergarten rooms with restrooms
  • A kitchen and cafeteria
  • Additional resource space
  • Art and music rooms
  • A new primary early learning playground
     

Fierke Construction Blueprint
Please click the image above for a larger version.

Project Timeline

Construction will begin in July 2018 and be completed in May 2019.

Updates

Please check back regularly for updates on the construction at Fierke.

October 15, 2018

Storm sewer work and retention pond excavation is now complete. The main sanitary line for the addition is in progress and the support steel installation began last week. In the coming weeks, steel columns, beams, and roof decking will continue followed by interior framing.



September 10, 2018

The underground plumbing for the building addition has been finished. Stone sub base work will soon be completed followed by the pouring of the concrete slab. Storm sewer work is also set to begin.  Work on the extension of existing roof drains is in progress. 

August 20, 2018

New fire sprinkler piping, domestic water piping, electric, and boiler piping has been installed in both locker rooms. A new suspended ceiling tile system has been installed in both locker rooms which will be ready for students on the August 23. The new roof over the locker rooms has also been installed. Concrete footings and foundation walls for the addition have been poured. 


August 6, 2018

Construction fencing was completed and excavation on the south side of the building is in progress. Work on the Boiler piping, domestic water lines, electrical conduit, and sprinkler piping in the existing school building has been completed.

Support steel to accommodate the new roof in the locker rooms has been completed and the new parapet walls above the locker room have been installed.

July 16, 2018

Construction fencing has been installed. Demolition work has started in both locker room areas. This work includes removing the suspended ceiling, sprinkler system piping, HVAC piping and electrical lighting system to accommodate the roof re-design. 